Message from the Chairman!!!

Hi guys,
Hope u r ok.
We had a good time on saturday. the turn up was big (40 and more people). i was so shocked the campusors are really many. So we gave them some encouragement before introducing the main item on the agenda - Luwero.
We had some sort of funraisind including selling cups of tea and biscuits. Nicholas you can pay for your tea am keeping it.
We collected just over 100k in cash and pledges amounted to a whooping 800+ k. our challenge is to collect that money from the people.

We expected that if we collect all the money with in the one month period we gave our selves, we should be starting to build in July. So we will expect your contributions also by then. Pliz talk to as many people as you can who can buy into this idea and support us find below the expected budget.

Note current rates:
1 US Dollar = UGX 1793, 1 Pound Sterling = UGX 3363, 1 Euro = UGX 2300

Costings
Shelter HOUSE PLAN
Item Unit Amount Unit Cost Total Size
Trench excavation Unit 1 50,000 50,000 Lounge 4.0 x 3.5 m
Primary Materials Bedroom 3.0 x 3.5 m
Cement Bags 22 18,000 396,000




4.0 m 3.5 m
Plaster Sand Trips 3 40,000 120,000
Aggregates Trips 1 50,000 50,000
Bricks No 4000 100 400,000
Iron Sheets Pieces 14 13,000 182,000
Ridges Pieces 4 6,000 24,000 Lounge Bedroom 3.5 m
Timber Pieces 18 3,500 63,000



Ventillators No 10 250 2,500
Nails Kgs 8 2,000 16,000
Windows No 2 20,000 40,000
Locks No 1 5,000 5,000
Casement Doors No 1 40,000 40,000
DPC Unit 1 5,000 5,000
Poles No 20,000 0
Sub Total 1,393,500
Labour Unit 1 300,000 300,000
Misceleneous Unit 1 250,000 250,000
Primary Total 1,943,500

Floor Slab
Cement Bags 3 18,000 54,000
Plaster Sand Trips 1 40,000 40,000
Aggregates Trips 0.5 50,000 25,000
Labour Unit 1 30,000 30,000
Total 149,000